• 3 Classroom Additions

    LCPS Senior Project Manager: Hal Broadhurst
    LCPS Project Managers: Charlie Hall, Sam Sakati

    Contractor: HESS Construction + Engineering Services, Inc., Gaithersburg, MD
    Architect: Hord Coplan Macht, Baltimore, MD
    Civil Engineer: Bowman Consulting, Leesburg, VA

    CIP Funding - FY2017
    Construction Began – Spring of 2017
    Project Completion – Summer 2018

    Six elementary schools in the Dulles North and Dulles South area will have 3-classroom additions made to facilitate the expansion of full-day kindergarten or other elementary needs. Construction will begin in spring of 2017 and will be completed by the start of the 2018-19 school year. The schools identified for the 3-classroom additions are Arcola, Creighton's Corner, Legacy, Liberty, Pinebrook, and Rosa Lee Carter Elementary Schools.