- Broad Run HS Classroom Addition Phase 1
Construction
Page Navigation
-
Broad Run High School Classroom Addition & Renewal
Phase 1 Construction -- Bus Loop & Additional Parking
LCPS Civil Engineer: Gary Vanalstyne
LCPS Civil Engineering Coordinator: Claus Bader
Contractor: Leo Construction
Civil Engineer: J2 EngineersFunding – FY2015
Proposed Bid/Construction Start Dates – Spring 2015
Project Completion – Summer 2016The Broad Run High School classroom addition and renewal project will be completed by the start of the 2016-17 academic year. The addition at Broad Run High School will involve the construction of ten classrooms to replace the existing nine trailers on site as well as expansion of the cafeteria, two resource spaces, a health room, an orchestra room, and improvements to the auditorium and overall student circulation. The project will also include a new senior parking lot to replace the existing parking lot removed for the classroom addition. The school’s bus loop will be extended and include ADA (Americans with Disabilities Act of 1990) improvements. The onsite fuel facility for LCPS and County-owned vehicles will be removed. Improvements associated with the athletic program include drainage improvements; ticket booth upgrades; new or renovated press boxes for the softball, baseball, and stadium fields; new restroom facilities; a team building; ADA compliant paths; stadium synthetic turf and track replacement; and a new shot put area. Grading of the band practice area, parking lot expansion and resurfacing will also be a part of the project scope.
Phase 1 of the Broad Run HS Renewal Project has been completed and provides much needed parking and school bus capacity for the 2015 school year.
The Phase 1 work included a new bus loop extension to accommodate an additional 14 school buses on-site, improved bus circulation, and a new 73 space parking lot near Ashburn Road. The bus loop was completed in August 2014 and the parking lot was available in September 2014.
As the majority of the BRHS Renewal project work will be completed from April 2015 to August 2016, this Phase 1 work allows the school year operations to function at a higher level during the Phase 2 construction process.
If you have questions regarding the Broad Run HS Classroom Addition & Renewal project or after-hours work at the site, please contact the office of Construction Services at 571-252-1161.
Completed Bus Loop & Senior Parking Lot